CONSTRUCTION: 2026 Outlook

Please review the following construction projects planned to be completed in the 48th Ward in 2026. Click on a project on the map to learn more about it, or see the projects in list form below. Note that dates are subject to change. Have a question about one of these projects? Call us at 773-784-5277 or send an email to info@the48thward.org. You can also search for and track the progress of local projects via ChiStreetWork.



Q1 (January-March)

  • Berwyn/Ashland Traffic Light

    • Note: This traffic light is part of the Berwyn Greenway project, making it safer for cyclists to get to the Lakefront Trail.

Q2 (April-June)

  • Arterial Lighting Sheridan (Catalpa to Berwyn)

  • Ridge/Wayne Pedestrian Hybrid Beacon

  • Broadway Refuge Islands (at Hood, Rosedale, and Norwood)

  • Berwyn Greenway Pavement Markings in the Meadows

  • Street Resurfacing

    • Ardmore (Sheridan to Winthrop)

    • Glenwood (Balmoral to Berwyn)

    • Glenwood (Bryn Mawr to Ridge)

    • Glenwood (Ardmore to Rosedale)

    • Balmoral (Wayne to Lakewood)

  • Alley Resurfacing

    • Winona/Foster/Sheridan/Marine

    • Highland/Rosemont/Clark/Greenview

    • Elmdale/Thorndale/Magnolia/Broadway

    • Glenwood/Ridge/Hollywood

    • Winona/Argyle/Winthrop/Kenmore

    • McCutcheon/Margate/Marine/Ainslie

    • Kenmore/Winona/Sheridan/Argyle

    • Clark/Hollywood/Glenwood/Olive

  • Accessible Pedestrian Signals

    • Broadway & Balmoral

    • Sheridan & Balmoral

    • Sheridan & Glenlake

    • Sheridan & Argyle

    • Broadway & Argyle

    • Broadway & Ainslie

  • Detached Bump Outs

    • Clark & Gregory

  • Sidewalks

    • 940 W Glenlake

    • 5840 N Broadway

Q3 (July-September)

  • DWM Water Main Project - Sheridan/Bryn Mawr

    • Scope: Sheridan (Bryn Mawr to Foster) and Bryn Mawr (Sheridan to Kenmore)

  • Raised Intersections near Senn (Thorndale/Glenwood & Ardmore/Glenwood)

  • Bump Outs - Summer 2026

    • Olive/Glenwood

    • Hollywood/Clark

  • Under-L Activation

  • Green Alleys

    • Balmoral/Summerdale/Clark/Glenwood

    • Bryn Mawr/Catalpa/Broadway/Railroad

    • Ardmore/Hollywood/Winthrop/Kenmore

Q4 (October-December)

  • Elise Malary Plaza

    People’s Gas System Improvement Projects

    • Bryn Mawr (Broadway to Kenmore)

    • Sheridan & Ardmore

  • Curb Extensions

    • Foster & Wayne

Date TBD

  • CDOT Lighting Projects

    • 6145-6212 N Lakewood

    • Edgewater (Glenwood to Clark)

    • Granville (Broadway to Glenwood)

  • Sewer Lining Project

    • Alley west of Ridge (W Victoria St to 1 Section South of W Victoria St)