Construction Updates: October 30, 2024

48th Ward Construction Header with illustration of a traffic cone

Please be advised of the following upcoming and ongoing construction in the ward:


New Public Seating on Bryn Mawr

Thanks to CDOT for installing these two new public seating arrangements on the northeast corner of Bryn Mawr and Broadway and the northwest corner or Bryn Mawr and Winthrop!


red crane at bryn mawr construction site

RPM Extended Road and Alley Closures

The following roads and alleys in the ward will be closed due to the Red and Purple Modernization (RPM) project:


SPECIAL NOTICE: BRYN MAWR EXTENDED WESTBOUND LANE CLOSURE

 CTA has begun street/sewer reconstruction, and station utility connection work on the west side of Bryn Mawr between Broadway and Winthrop. Westbound lane closures on this stretch of Bryn Mawr are expected to continue through Saturday, December 14. Read a full list of impacts here.


24/7 Street Closures
Balmoral from Broadway - Winthrop

  • NEW DATES: Saturday, October 12 - Saturday, November 2

  • Work Activity: Street & Sidewalk Restoration

Argyle at the CTA Tracks

  • Monday, November 4 - Thursday, November 7

  • Work Activity: Precast Station Platform Installation

WESTBOUND LANE CLOSURE: Berwyn from Winthrop - CTA Tracks

  • Monday, October 28 - Friday, November 8

  • Work Activity: DWM Station Utility Work

Intermittent Daily & Nightly Street Closures
Ardmore at the CTA Tracks

  • NEW DATES: Saturday, October 26 - Friday, November 8

  • Work Activity: Material Delivery for Trackwork & Final Asphalt

Daily Short-Term Street Closures
Winona at the CTA Tracks

  • Monday, September 23 - Saturday, November 9

  • Work Activity: Crane Staging & Concrete Placement

  • Roughly 11 short-term daily closures expected within the above date range 

Extended Alley Closures
Alley east of 5239 - 5259 N Broadway

  • Wednesday, October 23 - Thursday, October 31

  • Work Activity: Concrete Placement

Alley west of 5000 - 5062 N Winthrop

  • Tuesday, October 29 - Saturday, November 23

  • Work Activity: Alley Reconstruction

Please note that additional sidewalks, alleys, and streets in the ward may be affected by partial closures. Visit the RPM site to subscribe for all updates in your area.


If you have any questions regarding a project not posted, please reach out to development@the48thward.org. Likewise, if you would like to know about any upcoming project in the ward, visit ChiStreetWork.

Subscribe to the 48th ward newsletter for more updates.

Be sure to review last week's construction update as some projects may be ongoing.