Current Sidewalk Improvment Projects
Please be advised of sidewalks improvements are taking place near the following addresses:
6007 N Kenmore
5649 N Magnolia
5353 N Kenmore
1019 W Balmoral
5244 N Wayne
Due to recent weather, some of these projects may have started earlier than expected. Others may be slightly delayed. We appreciate your patience as CDOT works diligently to make these improvements.
Residential Lighting Improvements
Residential lighting improvements are coming to the stretch of Berwyn between Clark and Glenwood. Note that CDOT vehicles may occupy some parking spaces as they complete this work.
Green Alley Bounded by Wayne, Glenwood, Hollywood, and Bryn Mawr
Both east-west legs of the alley have been completed. The north-south leg of the project is expected to be completed on August 5. See a progress picture above. Read more and see a project map here.
Upcoming Alley Construction
Later this year, construction will begin on the alley bounded by Victoria, Edgewater, Clark, and Ridge. Neighbors will receive an additional notice approximately one week before work begins.
During construction:
Residential garbage will be curbside. Homeowners are asked to relocate cans to the front of the property.
There will be no alley access for approximately six weeks (depending on weather conditions).
Barricades will block all entrance to the alley. Residents are advised to seek alternative parking.
This project will be managed by the CDOT. For more information, please contact 312-722-6590.
Kenmore Resurfacing - Weather Delays
The Kenmore resurfacing projects continues to be delayed due to recent inclement weather. Our office is communicating with CDOT to get an updated timeline. In the meantime, please be on the lookout for no parking signs that may be posted soon. Thank you for your continued patience as we complete these improvements.
Hollywood Avenue Resurfacing
Reminder that Hollywood from Ridge-Sheridan will be resurfaced starting July 24 (weather permitting). We will share updates regarding potential lane shifts and closures as we receive them.
RPM Extended Road and Alley Closures
The following roads and alleys in the ward will be closed due to the Red and Purple Modernization (RPM) project:
Street & Alley Closures / Traffic Lane Shifts
Foster between Broadway and Winthrop Avenue
Monday, June 24 - Friday, August 2
Work Activity: Street & Sewer Reconstruction
See the full list of impacts from this work here.
Street Closures
Hollywood Avenue from Broadway to Winthrop
(Lane Closures and Traffic Shifts)
Tuesday, May 28 - Wednesday, July 17
Work Activity: Station Utility Work & Street Reconstruction
Ardmore from Broadway to Winthrop
Wednesday, July 24 - Tuesday, August 13
Work Activity: Street & Sidewalk Restoration
Balmoral at the CTA Tracks
Wednesday, July 10 - Friday, August 30
Work Activity: Track Structure Segment Delivery
Alley Closures
Alley west of 5200 - 5268 N Winthrop &
Alley east of 5201 - 5259 N Broadway
Friday, May 24 - Wednesday, July 31
Work Activity: Permanent Station Foundation Construction
Alley behind 5700 - 5758 N Winthrop
Wednesday, July 24 - Tuesday, August 13
Work Activity: Alley Reconstruction
Alternative parking at 5826 N Broadway and 5840 N Broadway.
Noise Alerts
CTA Tracks from Sunnyside Avenue - Kenmore
Monday, July 8 - Friday, July 26
Work Activity: Lead Abatement & Painting
Please note that sidewalks and additional alleys in the ward may be affected by partial closures. Visit the RPM site to subscribe for all updates in your area.
If you have any questions regarding a project not posted, please reach out to development@the48thward.org. Likewise, if you would like to know about any upcoming project in the ward, visit ChiStreetWork.
Subscribe to the 48th ward newsletter for more updates.
Be sure to review last week's construction update as some projects may be ongoing.