Construction Updates: July 17, 2024

Please be advised of the following upcoming and ongoing construction in the ward:


Current Sidewalk Improvment Projects

Please be advised of sidewalks improvements are taking place near the following addresses: 

  • 6007 N Kenmore

  • 5649 N Magnolia

  • 5353 N Kenmore

  • 1019 W Balmoral

  • 5244 N Wayne

Due to recent weather, some of these projects may have started earlier than expected. Others may be slightly delayed. We appreciate your patience as CDOT works diligently to make these improvements.


Residential Lighting Improvements

Residential lighting improvements are coming to the stretch of Berwyn between Clark and Glenwood. Note that CDOT vehicles may occupy some parking spaces as they complete this work. 


wayne green alley progress photo

Green Alley Bounded by Wayne, Glenwood, Hollywood, and Bryn Mawr

Both east-west legs of the alley have been completed. The north-south leg of the project is expected to be completed on August 5. See a progress picture above. Read more and see a project map here


Upcoming Alley Construction

Later this year, construction will begin on the alley bounded by Victoria, Edgewater, Clark, and Ridge. Neighbors will receive an additional notice approximately one week before work begins. 

During construction:

  • Residential garbage will be curbside. Homeowners are asked to relocate cans to the front of the property.

  • There will be no alley access for approximately six weeks (depending on weather conditions).

  • Barricades will block all entrance to the alley. Residents are advised to seek alternative parking.

This project will be managed by the CDOT. For more information, please contact 312-722-6590.


Kenmore Resurfacing - Weather Delays

The Kenmore resurfacing projects continues to be delayed due to recent inclement weather. Our office is communicating with CDOT to get an updated timeline. In the meantime, please be on the lookout for no parking signs that may be posted soon. Thank you for your continued patience as we complete these improvements.


Hollywood Avenue Resurfacing

Reminder that Hollywood from Ridge-Sheridan will be resurfaced starting July 24 (weather permitting). We will share updates regarding potential lane shifts and closures as we receive them.


RPM Extended Road and Alley Closures

The following roads and alleys in the ward will be closed due to the Red and Purple Modernization (RPM) project:

Street & Alley Closures / Traffic Lane Shifts
Foster between Broadway and Winthrop Avenue

  • Monday, June 24 - Friday, August 2

  • Work Activity: Street & Sewer Reconstruction

  • See the full list of impacts from this work here.

Street Closures
Hollywood Avenue from Broadway to Winthrop
(Lane Closures and Traffic Shifts)

  • Tuesday, May 28 - Wednesday, July 17

  • Work Activity: Station Utility Work & Street Reconstruction

Ardmore from Broadway to Winthrop

  • Wednesday, July 24 - Tuesday, August 13

  • Work Activity: Street & Sidewalk Restoration

Balmoral at the CTA Tracks

  • Wednesday, July 10 - Friday, August 30

  • Work Activity: Track Structure Segment Delivery

Alley Closures
Alley west of 5200 - 5268 N Winthrop &
Alley east of 5201 - 5259 N Broadway

  • Friday, May 24 - Wednesday, July 31

  • Work Activity: Permanent Station Foundation Construction

Alley behind 5700 - 5758 N Winthrop

  • Wednesday, July 24 - Tuesday, August 13

  • Work Activity: Alley Reconstruction

  • Alternative parking at 5826 N Broadway and 5840 N Broadway.

Noise Alerts
CTA Tracks from Sunnyside Avenue - Kenmore

  • Monday, July 8 - Friday, July 26

  • Work Activity: Lead Abatement & Painting

Please note that sidewalks and additional alleys in the ward may be affected by partial closures. Visit the RPM site to subscribe for all updates in your area.


If you have any questions regarding a project not posted, please reach out to development@the48thward.org. Likewise, if you would like to know about any upcoming project in the ward, visit ChiStreetWork.

Subscribe to the 48th ward newsletter for more updates.

Be sure to review last week's construction update as some projects may be ongoing.