Construction Updates: August 28, 2024
Please be advised of the following upcoming and ongoing construction in the ward:
DuSable Lake Shore Drive Resurfacing: Phase II
Resurfacing on DLSD between Hollywood and Lawrence is scheduled to resume on Tuesday, September 3 pending issues with exisiting utilities and weather. This is part of Phase II of the CDOT Arterial Resurfacing - North Area Project. During Phase II, CDOT will be paving and installing permanent paving markings. All work is scheduled to be completed by the end of October, 2024. See a list of Phase II impacts below:
temporary nightly lane closures will ber in effect as necessary
work will require a combination of partial and full lane closures
Weekday nighttime multi-lane closures will be in effect from 7-9pm
Nighttime full-lane closures will be in effect from 9am-6am
Sunday nighttime full-lane closures will be in effect from 3pm-6am
All lanes will be opened on a daily basis by 6am
Phase I, which was completed this spring, involved pavement patching and curb/gutter removal and replacement.
Berwyn Greenway Progress Update
Work on the Berwyn Greenway is well underway! Next time you're on Sheridan, check out the brand new paint connecting Berwyn to the Lakefront Trail! This greenway will span all the way from the North Shore Channel Trail to the Lakefront Trail! Read more about the full scope of the project here.
Interactive Street and Alley Resurfacing Map
During our recent Infrastructure Town Hall, we gave an overview of streets that will be resurfaced and alleys that are due for repaving and other improvements in 2024/2025. See an interactive map of these projects here. Click on individual streets and alleys for work details and timelines.
Upcoming Park Improvement Projects
We're excited to see many improvements coming to our 48th ward parks this year and next! Having secured funds for trail repaving and a new playground soft surface at Margate Park, our office is now working on funding a Cochran Park redesign, drainage and sidewalk improvements at the Bryn Mawr dog-friendly area, and a Nature Playspace at Senn Playground. Read more about these projects on our blog.
RPM Extended Road and Alley Closures
The following roads and alleys in the ward will be closed due to the Red and Purple Modernization (RPM) project:
Extended Parking Lane Closure & Traffic Shifts
Foster Avenue from Broadway - Winthrop Avenue
Sunday, August 25 - Saturday, September 28
Work Activity: Street Reconstruction & Shoring Tower Construction & Staging
Single Day Closures
Winona at the CTA Tracks
3 single-day closures between Wednesday, August 28 and Tuesday, October 1
Community to be notified 48 hours in advance of each single-day closure
Work Activity: Concrete Placement & Shoring Tower Construction & Staging
24/7 Street Closures
Ardmore from Broadway - Winthrop
NEW DATES: Friday, August 23 - Saturday, September 7
Work Activity: Street, Sidewalk Restoration & Screen Wall Installation
Catalpa from Broadway - Winthrop
Thursday, August 22 - Saturday, September 28
Work Activity: Street & Sidewalk Restoration
Alley Closuress
Alley behind 5700 - 5758 N Winthrop
NEW DATES: Friday, August 9 - Saturday, August 31
Work Activity: Alley Reconstruction
Alternative parking at 5826 N Broadway and 5840 N Broadway.
Please note that sidewalks and additional alleys in the ward may be affected by partial closures. Visit the RPM site to subscribe for all updates in your area.
If you have any questions regarding a project not posted, please reach out to development@the48thward.org. Likewise, if you would like to know about any upcoming project in the ward, visit ChiStreetWork.
Subscribe to the 48th ward newsletter for more updates.
Be sure to review last week's construction update as some projects may be ongoing.